Vijayawada Bypass

vijayawada Bypass

It is 48km length bypass divided into packages 3 & 4. Package3 consists of 30km from chinavutupalli to gollapudi and package-4 consists of 18km from gollapudi to chinakakani

Bypass status: (Nov-2024)

 Package-3

On Bike: One can travel on the entire pakcage-3 that is from Gollapudi to Chinavutupalli .But at few locations works not completed.

By car you can travel from nunna to chinavutupalli only

Drive carefully during night times, since the highway is complete at few locations.

Package-4
Works are going on , and it may take 1.5 yrs for completion

vijayawada bypass
Krishna River Bridge, Dt: Dec-2023